Minutes from the 2/9/09 MOMSAH Meeting

From: Mike Cregan Attending: EB, Mike C., Jeremy M., Anne H., Hobbie P., Joe, Lynn, Richard F. * Anne H. will increase the urgency for Lane’s environmental contact to connect with Whole Builders via Jeremy or Mike, as we are at a critical decision point. o    The group as a whole is open to have… Read More

Preparing for the 2/9/09 MOMSAH meeting

MOMSAH met Monday February 9. In anticipation of that meeting the team of  Carolyn, EB, Jeremy & Mike got the following two documents: 1. An updated “Cost Summary Report” from Whole Builders. wb-report-090206 An earlier version had been the subject of much discussion with Whole Builders, and this was their attempt to summarize our mutual… Read More